W. 20th Avenue - Quail Street Park to Nelson Street Project

W. 20th Avenue Sidewalk and Drainage Improvements Project – Quail Park to Nelson Street

Project Description
This project will install sidewalk, curb and gutter, and storm sewer inlets and pipes on the south side of 20th Avenue from Quail Street Park to Nelson Street. With the installation of storm sewer, the existing ditches and cross culverts on the south side of 20th Avenue will be removed, and the sidewalk will be continuous from Simms Street to Kipling Street.

May 2026 Update

Recently Completed Work
All storm sewer installation has been completed. Sidewalk, curb and gutter, and curb ramps between Quail Street Park and Owens Court and Nelson Street and Newcombe Street has been completed. Initial asphalt paving operations have started.

Current Work
Final sidewalk, curb and gutter, and curb ramps are being completed at 20th Avenue and Oak Street. Pavement operations will continue through mid-May.

Upcoming Work
Final grading and paving is scheduled for early May, as is landscape, fencing and irrigation restoration along 20th Avenue. Sidewalk, irrigation, and landscaping will continue in Quail Street Park. For more information on the improvements in Quail Park, including a site layout and proposed rendering, please see our Lakewood Together page.

Traffic Impacts
W. 20th Avenue will be closed to eastbound traffic between Quail Street and Nelson Street during construction. Detours will be in place to avoid this closure. Only westbound traffic will be allowed through the work zone.

Target Project Completion
The project is estimated to be completed in the early-summer of 2026.