Project DescriptionThis project will install a storm sewer on the west side of Welch Street to mitigate localize flooding on Welch Street. Inlets along the curb will be installed to collect stormwater runoff. The system will outfall into Lakewood Gulch on the west side of Welch Street.
April 2026 Update
Recently Completed WorkThis project was completed on 4/10/2026 after final stabilization and seeding were complete.
Upcoming WorkNone
Traffic ImpactsWelch Street is open to traffic.
Target Project CompletionComplete